ACTION TAKEN: APPROVED
APPROVE CHANGE ORDER NO. ONE TO EAS CONTRACTING, L. P. FOR CONTRACT NO. 2004-204, EL PASO INTERNATIONAL AIRPORT AIRFIELD LIGHTING AND CONTROLS PROJECT FOR AN INCREASED AMOUNT OF $779,983.45, AS FOLLOWS:
SCOPE CHANGE: REPLACE 203 SIGNS OF VARIOUS TYPES FROM 1 TO 7 MODULES ON THE AIRFIELD. ADD 60 CALENDAR DAYS TO CONTRACT TIME. $834,911.00
CONSTRUCTION CHANGE: REVISE LINE ITEMS IN CONTRACT TO ALLOW FOR PAYMENT OF TEMPORARY WIRING, LIGHTS, AND SIGNS TO REFLECT ACTUAL ONSITE CONDITIONS; REVISE CONTRACT LINE ITEMS FOR SEVERAL DUCT BANK CONFIGURATIONS THAT ARE REQUIRED BETWEEN THE HANDHOLE AND THE END OF THE CASING FOR THE BORES UNDER THE TAXIWAYS AND RUNWAY TO REFLECT ACTUAL REQUIREMENTS; CREDIT IS ALSO BEING PROVIDED FOR MATERIAL NOT USED IN TAXIWAY K2 BORE. <$54,927.55>