Construction Update: Upper Valley Rd. Street & Drainage Improvements
April 16, 2010 - Please note that as part of necessary construction activities to finalize the Upper Valley Rd. Street & Drainage Improvement (Roundabout) Project, effective Monday, April 19, 2010, Country Club Rd. will be closed to eastbound traffic from Westside Dr. to River Run St. and Upper Valley Rd. will be closed to traffic from Gomez Rd. to Country Club Rd.  for approximately one week.  These temporary road closures will allow for the placement of final finishes to include roadway striping and markings along Country Club Rd.

Eastbound traffic traveling on Country Club Rd. will be diverted onto Westside Dr. toward Artcraft Dr.. Access will continue to be available to westbound traffic on County Club Rd. throughout this temporary period. Message boards have been installed to advise the traveling public.

 

Additional Highlights

 

  • Expected  project completion in late April 2010
  • Construction cost of approximately $ 1.9 million

 

Background

 

The scope of work for this project consists of the construction of a new Roundabout at the intersection of Upper Valley Rd., River Run St. and Country Club Rd. .  The project features the following enhancements:

 

  • New underground drainage structure
  • Custom artwork
  • Street Lighting
  • Landscaping
  • Concrete Pavement

 