|
Storm 2006 Capital Project Update
As part of the ongoing initiative addressing the critical repair and reconstruction priorities that resulted from Storm 2006, three major projects reach the final stages of construction substantially improving stormwater management capabilities in the community.
The project providing street, utility and drainage improvements on Baltimore Street, Glory Road and Oregon Street is now open to traffic. Additionally, the James Watt and Lee Trevino project opens to traffic and repair work improving the Thunderbird Valley Channel also nears completion.
Baltimore Street/Glory Road
Construction on the complete sewer re-route benefiting the Baltimore, Glory Road and Oregon Street area, opened to traffic early October with substantial completion expected this month. The project scope consisted of the following improvements:
Installation of an underground system consisting of approximately 1,500 linear feet of a 6ft wide by 4ft high box culvert providing expanded water capacity
Storm system connection to the existing network in Glory Road
New curb and gutter, sidewalks, wheelchair ramps, pavement structure and landscaping
Additional project highlights include:
- Project start date of February 12, 2007
- Total cost of approximately $1.5 million
James Watt & Lee Trevino
The James Watt & Lee Trevino project focused on various street and drainage improvements needed to alleviate flooding at this intersection. Prior lane closures throughout the construction period opened to traffic mid-October. Some additional drainage work is in progress; however, additional road closures are not anticipated.
The overall project scope featured the following enhancements:
New roadway pavement
Replacement of a concrete flume with energy dissipation structure to the Jesuit Basin
Installation of new sidewalk, driveways and fencing as necessary
Construction and placement of curb and gutter and ADA compliant ramps
Adjustments to utilities and medians
Additional project highlights include:
- Project start date of May 30, 2007
- Total cost of approximately $435,000
Thunderbird Valley Channel
Repair work required in the Thunderbird Valley Diversion Channel project is expected to complete ahead of schedule this November with the channel fully functional at this time. The scope of work provides for the efficient drainage flow through the channel and included the following improvements:
Removal and replacement of existing concrete channel lining
Removal and replacement of pavement structure and existing chain link fencing
Replacement of earthwork in scoured regions and pipe underdrains
Additional project highlights include:
- Project start date of May 7, 2007
- Total cost of approximately $591,000
Print Version
Newsletter produced by the City Communications & Public Affairs Office.
If you would like to subscribe to receive the Community Newsletter, send an email to communitynewsletter@elpasotexas.gov, with your name and email address.
|
|